Price
Free
Execution deadline in working days
5 working days
Recipient
Any person
Receiving restrictions
-

The explanatory memorandum shall include the conditions for the commencement of works and the requirement to provide information on the performer of works.

After the receipt of the necessary information and documents for the construction work of the first group, the State Railway Technical Inspectorate shall make a note in the Construction Information System regarding the fulfilment of the conditions for the commencement of works.

The submission shall be submitted through the Construction Information System to the State Railway Technical Inspectorate.

 

  1. Construction Law
  2. Cabinet of Ministers 02.09.2014. regulations no. 530 "Railway construction regulations"
  3. Cabinet of Ministers 19.08.2014. regulations no. 500 "General building regulations"