Price
Free of charge
Execution deadline in working days
10 days
Recipient
Any person
Receiving restrictions
-

An application for changes to the construction permit shall be submitted in cases where it is necessary to change the conditions of the construction permit. . The submission shall be accompanied by appropriate changes to the minimum composition of the building design.

A decision of the State Railway Technical Inspectorate regarding the performance of changes to the construction permit and the actual data of the construction permit shall be available in the construction information system.

The submission shall be submitted through the Construction Information System to the State Railway Technical Inspectorate.

 

  1. Construction Law
  2. Cabinet of Ministers 02.09.2014. regulations no. 530 "Railway construction regulations"
  3. Cabinet of Ministers 19.08.2014. regulations no. 500 "General building regulations"