For temporary authorisation:
-
- Applicant shall be submitted to the application in which the following shall be indicated:
-
description and identification of the stacionary equipment;
-
details of the technical characteristics of the fixed installation;
-
planned pre-commissioning use;
- the planned testing programme;
- information on the planned time period for carrying out the checks;
- a statement by the holder of the single safety certificate or safety certificate that the testing will be carried out in accordance with the conditions of the single safety certificate or safety certificate;
- an independent assessor's report on the application of the common security method for risk assessment in accordance with the risk Regulation, which also assesses the management of interfaces. The risk assessment relating to changes in the railway system as well as to the use of pre-commissioning, including testing, should cover safety impacts to ensure safe use of the fixed installation in this mode.
-
- Inspection:
- within one month, the documents submitted shall be evaluated;
- take a decision to issue a provisional authorisation.
- Applicant shall be submitted to the application in which the following shall be indicated: